Support Installations at Mäntsälä Data Center – Two Separate Buildings.
Makinakorjaamo* was invited to bid—on Hilti’s recommendation—for the installation of Hilti MQ support systems in a new data center project.
The timeline was exceptionally tight. We immediately understood the challenge: the previous contractor had refused to even bid after seeing the schedule.
Together with the Client’s representative, we conducted three coordination workshops in English with all installation partners.
The result was a mutually accepted, detailed construction timeline.
Operational efficiency know-how | Solid background with tough references | Trusted MQ installation partner for Hilti in Finland | Mindset: Always on-time.
Within one month, we launched three fast-track recruitment campaigns and more than doubled our employment contracts. Success was made possible by:
Makinakorjaamo’s reputation as an employer
We take care of our people. In addition to salary, we share profits with employees when the company succeeds.
Trusted recruitment partners
We combine strong recruitment partners with AI-driven sourcing. In Mantsala, we brought in 8 new hires in 10 days—from “go” to boots on the customer’s site.
CEO’s Background in Professional Recruitment
Double MBA and 25 years of hands-on leadership—from business consulting to mechanical installation projects. Deep understanding from HR to CxO level. Successfully recruited hundreds of people across multiple industries.

Our site supervisors and 3–4 of our most experienced technicians came from Makina
Their role: to ensure correct interpretation of drawings and maximize installation speed.
In addition, we appointed:
Installation started in mid-April—just one week after contract award. Work progressed well in May–June.
Then the Client requested an accelerated schedule: they wanted the first building completed 30 days earlier than agreed. We recalculated and hired 4 more installers, on fixed-term contracts until the end of August.
Everything worked. We pulled off what had seemed impossible.
When the first building was completed, the Client requested an offer for the second building—with an even tighter timeline, removing another 25 days. Total reduction: 55 days.
After careful consideration, we accepted.
This required:
A double-revenue project, completed 55 days ahead of schedule—a schedule so demanding that many competitors wouldn’t even bid.